Mobina Projects

Sarcheshmeh complex flash smelter project


Starting date: 11 Dec 2010 Finish date: 10 Jun 2014
Project goal: Design ,supply & construction of copper Flash smelter with 200,000 tons per annum capacity
Place : Iran - Kerman - Rafsanjan - Sarcheshmeh complex
Mobina scop of work : This project is defined for renovation of existing smelter. The existing Reverbratory furnaces replaced by Flash Smelting technology. Also the capacity of Sarcheshmeh smelter increase from 160,000 t/a to 300,000 t/a Anode copper from concentrate. Mobina scope of work includes basic design review, Local Basic and detail design. Procurement engineering services and site field engineering on EPC basis.
Mobina role : Design, engineering and supervisory services via EPC consortium
Client : National Iranian Copper Industries Co. Project consultant: HAK Engineering company
Technology and key equipment provider: Outotec - Finland
EPC contractor : Consortium of Sadid Jahan Sanat, Bamrah, Mobina and Fakoor sanat